Project Methodology — Tutor Management System

Development Methodology​

This project follows Scrum, an Agile framework built around fixed-length iterations ("sprints") that each produce a working increment of the software.

Why Scrum​

The course imposes fixed milestone deadlines (Sprint 1, 2, 3, Submission), which map naturally onto sprint boundaries — each milestone functions as a sprint with its own goal and scope. With a small team, Scrum's lightweight structure (a defined sprint goal, a tracked backlog, and iterative delivery) gives us enough process to stay coordinated without the overhead of a heavier framework.

  • Team size: 6

  • Sprint length: Variable, driven by the course's fixed milestone calendar rather than a uniform cadence: | Sprint | Start | End | Length | |---|---|---|---| | Sprint 1 | 2026-08-02 | 2026-08-25 | 23 days (~3.3 weeks) | | Sprint 2 | 2026-08-25 | 2026-09-15 | 21 days (3 weeks) | | Sprint 3 | 2026-09-15 | 2026-09-29 | 14 days (2 weeks) | | Wrap-up / stabilization | 2026-09-29 | 2026-10-11 | 12 days (~1.7 weeks) — final hardening and bug-fixing before submission, not a full sprint |

Roles​

  • Product Owner: Ndumiso Skhosana — owns the backlog and prioritizes features.
  • Scrum Master: Mogomotsi Motoma — facilitates ceremonies and removes blockers.
  • Development Team: Remaining members, responsible for implementation.

Scrum Ceremonies​

CeremonyFrequencyPurpose
Sprint PlanningStart of each sprintSelect and estimate backlog items for the sprint
Daily StandupDailyQuick sync — what was done, what's next, and any blockers
Sprint ReviewEnd of each sprintDemonstrate completed work to stakeholders
Sprint RetrospectiveEnd of each sprintReflect on the process — what worked and what can be improved

Sprint Logs​

Each sprint has its own page documenting that sprint's goal, scope, ceremonies held, and evidence. Pages are added as each sprint concludes.

  • Sprint 1 — 2026-08-02 → 2026-08-25
  • Sprint 2 — 2026-08-25 → 2026-09-15 (added at end of Sprint 2)
  • Sprint 3 — 2026-09-15 → 2026-09-29 (added at end of Sprint 3)
  • Wrap-up — 2026-09-29 → 2026-10-11 (added before submission)

Backlog & Task Tracking​

  • Tool used: Gitea Issues and Gitea Project
  • User stories are broken down into smaller tasks and tracked through the following workflow:
Backlog → To Do → In Progress → Done

Version Control & Branching​

  • Repository hosted on a self-hosted Gitea instance.
  • Feature work happens on descriptively-named branches following a <type>/<short-description> convention (e.g. feat/backend-routes-connectivity, chore/setup-webpages-frontend).
  • Changes are merged via Pull Requests, reviewed by at least one other team member before merging into main.
  • Commit messages describe the change and, where relevant, the branch/feature they belong to.

Continuous Integration / Continuous Deployment (CI/CD)​

Automated via Gitea Actions, triggered on every push to main:

  • Backend: installed, tested, and deployed to Azure App Service.
  • Frontend: built and deployed to Vercel.
  • Both jobs run independently, so a failure in one does not block the other.

Ceremony Adoption Status​

  • Sprint Planning: done - captured as the Gitea Milestone goal/scope above, with issues created and assigned against it.
  • Daily Standups: While daily standups are not currently conducted as a formal, documented ceremony, the team holds daily check-ins and discussions through WhatsApp to communicate progress, upcoming tasks, and any blockers.
  • Sprint Review: not yet formally documented.
  • Sprint Retrospective: not yet formally run for Sprint 1. Planned to be introduced from Sprint 2 onward. These ceremonies are being formalized going into Sprint 2, where the "Actively following methodology" criterion carries the same 10% weight and explicitly expects ongoing evidence.

Definition of Done​

A task/user story is considered Done when it:

  • Meets the acceptance criteria defined during sprint planning
  • Has been code-reviewed and merged via Pull Request
  • Passes CI checks (build, lint, tests where applicable)
  • Has been manually verified against the live/staging environment
  • Does not introduce regressions to existing functionality

Communication​

  • Tool used for team communication - WhatsApp, Gmail Spaces
  • Standups: format - text updates, live call

Evidence​

Evidence that this methodology is used (not just declared) is captured per-sprint on each sprint's page, since the rubric expects this to be shown as ongoing, not a one-time snapshot.